Ring-Pole Erection Procedure
|
|
1.
|
 |
Fit
adjustable bases with collars and lay out roughly in
position with their corresponding ledgers. Pick the
highest ground level for a setting out point to simplify
later adjustment. It helps if the screw jack is near
(not at) the bottom of the thread by allowing maximum
adjustment on lower ground levels. |
|
2.
|
 |
Connect
the legers to the rosette on the collar of the adjustable
base. DO NOT DRIVE HOME THE WEDGES AT THIS STAGE. |
|
3.
|
 |
Using
a spirit level, adjust the bases so that the ledgers
are horizontal. Accuracy in leveling at this stage eliminates
the need for further leveling and plumbing as the scaffold
is erected. |
|
4.
|
 |
Place
two aluminum planks or four 255mm (10") wide board
in each bay spanning the ledgers to square up the system.
Move progressively round the base of the scaffolding.
When squared and leveled, drive home the wedges. |
|
5.
|
 |
When
basing out is completed, the first standards are positioned
into the collar of the base. |
|
6.
|
 |
Ledgers
can now be placed at the required levels. |
|
7.
|
 |
Handrails
are automatically positioned. |
|
8.
|
 |
Planks
are now moved up to this first lift, decking out fully
if this is to be a working platform. |
|
9.
|
 |
Fix
diagonal braces across the face of the bays. Hammer
wedges home. |
|
10.
|
 |
The
scaffolding is completed by adding ledger midrails,
handrails and toe boards on the working platform. |
|
 |
Seacoast Scaffold
& Equipment Corporation |
163 Thadeus Street,
South Portland, ME 04106
(207)799-9800 (800)639-5042 Fax (207)799-9855
243 Sheep Davis
Road, Concord, NH 03302
(603)224-0999 (888)701-1119 Fax (603)224-1414
Email: info@seacoastscaffold.com

|